Multi-Discipline BIM Modeling from Scratch: Public Safety Facility, Atlanta, GA

From incomplete inputs to coordinated Structural and Architectural BIM models delivery for a 20,800 sq. ft. public Safety facility in Atlanta, GA

Get A Free Quote
Public safety facility banner
Overview

Project Overview

A multidisciplinary engineering consultancy in Atlanta engaged our team to develop fully coordinated Structural and Architectural BIM models for a 20,800 sq. ft. two-story institutional facility. Updated models were never made available by the broader design team, creating a critical coordination gap at the Construction Documents stage.

We deployed a dedicated BIM team, including an Architect, a Structural Engineer, and a Project Manager. Working from the available IFC model and issued construction drawings, the team independently developed all discipline models. Construction-ready content was delivered alongside high-quality Lumion renderings.

Level of Development LOD 300
Project Area 20,800 Sq.Ft.
Location Atlanta, GA
Manpower Used 3 Resources
Atlanta public safety facility BIM visualization
Tools We Use

Inside the Tools You Already Use

Delivery ran in Autodesk Revit and Lumion so coordinated models and visuals landed in platforms the project team already uses.

Autodesk RevitAutodesk Revit
LumionLumion
Project Deliverables

Input vs Output

From limited IFC and drawing inputs to coordinated multi-discipline BIM models and visualization outputs.

What We Received

  • IFC Architectural model
  • Construction drawing set
  • Verbal scope confirmation
  • Clarification responses

What We Delivered

  • Architectural model
  • Coordinated structural model
  • Coordination issue log
  • BIM marketing visuals
Get A Free Quote
Client Challenges

Pain Points of the Client

Missing and outdated discipline models blocked coordination at CD stage and put documentation accuracy at risk.

01

Updated Models Not Delivered

The design team did not provide updated Architectural, Structural, or MEPF models at the CD stage, leaving the client without a coordinated model set.

02

Incomplete Architectural Revisions

The architectural model had limited revisions and did not reflect the latest construction drawings, making it unreliable for coordination or documentation.

03

No Structural or MEPF Starting Point

Structural and MEPF models were not shared by the design team, leaving no baseline for building, coordinating, or validating engineering systems.

04

Coordination Gaps Across Disciplines

Interdisciplinary coordination stalled without updated models across all three disciplines, hindering discrepancy identification and resolution.

05

Risk of Downstream Documentation Errors

Proceeding with outdated or incomplete models risked propagating errors into construction documentation, permit packages, and contractor-facing deliverables.

06

Internal Capacity Constraints

The client's team could not rebuild and coordinate three discipline models while handling ongoing engineering and client responsibilities.

Our Approach

How We Solved It

An independent multi-discipline BIM team rebuilt models from available inputs and locked coordination through structured QC.

Independent Model Development

Architectural and Structural models were developed from the ground up using the available IFC model, construction drawings, and applicable standards.

Architectural Model Refinement

The available model was reviewed against revised PDFs. Missing walls, outdated elements, and furniture mismatches were corrected floor by floor.

Structural System Modeled from Scratch

The complete structural model was developed independently, covering framing, beams, columns, connections, and wall footings, with attention to complex junction conditions.

Structured Coordination List

A comprehensive coordination list was prepared at project outset, documenting all issues, responsible disciplines, and required actions for a traceable process.

Proactive Clarification Requests

Formal clarification requests were raised and documented for ambiguous items before modeling decisions were finalized and validated.

Day-Wise Work Planning with QC

Coordination items were distributed across a structured daily work plan, with dedicated QC hours allocated before each submission for accuracy.

Execution Strategy

End-to-End Project Delivery Through a Phase-Controlled Approach

The project was delivered across sequential stages, with each phase reviewed and confirmed before the team advanced. This phase-gated approach ensured that model content, coordination items, and client approvals were progressively locked in, reducing rework and maintaining forward momentum.

  1. Project Review and Coordination

    Project Review and Coordination

    01
    01

    Project Review and Coordination

    Project Review and Coordination

  2. 02

    Client Mark-Ups and Model Updates

    Client Mark-Ups and Model Updates

    02

    Client Mark-Ups and Model Updates

    Client Mark-Ups and Model Updates

  3. Structural and Building Modeling

    Structural and Building Modeling

    03
    03

    Structural and Building Modeling

    Structural and Building Modeling

  4. 04

    Material, Elevation, and Visualization Development

    Material, Elevation, and Visualization Development

    04

    Material, Elevation, and Visualization Development

    Material, Elevation, and Visualization Development

  5. Visualization Production and Final Rendering

    Visualization Production and Final Rendering

    05
    05

    Visualization Production and Final Rendering

    Visualization Production and Final Rendering

  6. 06

    Final Delivery and Submission

    Final Delivery and Submission

    06

    Final Delivery and Submission

    Final Delivery and Submission

Project Outcomes

Coordinated. Approved. Delivered.

End-to-end coordinated BIM delivery with validated models, resolved design gaps, and structured phase-gated execution.

Coordinated BIM Models at LOD 300

Delivered fully coordinated Architectural and Structural models at LOD 300.

Structured Multidisciplinary Issue Tracking

Documented all multidisciplinary discrepancies in a structured coordination list.

Architectural Discrepancy Resolution

Resolved first and second floor architectural discrepancies against latest drawings.

End-to-End Structural Model Development

Developed complete structural model from scratch, including complex junction conditions.

High-Quality Visualization and Marketing Outputs

Produced exterior renderings and BIM marketing visuals within tight timelines.

Phase-Gated Quality-Controlled Delivery

Maintained QC-verified, phase-gated delivery across four structured project stages.